Section 98-83. Issuance of certificate of completion.
(a) Upon completion of construction of the improvements, the applicant or his authorized representative shall provide to the city the following items:
(1) A letter stipulating that construction of the improvements has been completed and requesting final inspection and approval.
(2) The testing reports and certificates of compliance from material suppliers specified in this chapter.
(3) Two sets of as-built construction plans.
(4) A letter signed and sealed by a professional engineer registered in the state certifying that the improvements have been constructed in conformity with the approved construction plans and specifications.
(5) A letter from the appropriate authority approving all utility installations. If the authority is accepting a public water or sanitary sewer system, there must be a letter indicating acceptance of the construction of the system.
(b) Upon receipt of the items listed in subsection (a) of this section, the city shall review the data and make a final inspection of the constructed improvements and shall notify the applicant of any items of noncompliance of the construction with the design contained in the approved construction plans and specifications and the provisions and requirements of this chapter. A certificate of acceptance shall be issued by the city when the construction of the improvements is completed in conformity with the design contained in the approved construction plans and specifications, and the provisions and requirements of this chapter.
Secs. 98-84, 98-85. Reserved.